Road closure during next phase of Bishopbriggs Relief Road

The road closure will start on January 7

The road closure will start on January 7

Part of a busy road will close for more than seven weeks at the start of the new year as work is carried out on Bishopbriggs Relief Road.

Westerhill Road will be shut from Tuesday, January 7, until Friday, February 28, from its junction with Robroyston Road to Wester Cleddens Road, which comes under the North Lanarkshire Council area.

Work will take place to build a new roundabout.

Alternative routes will be in place and local access will be maintained during the closure.

Taylor Wimpey West Scotland is building the third section of the road, which will extend from Auchiniarn to Wester Cleddens Road.

The road building - which got underway in July - coincides with the construction of 196 homes to the east of Miller Drive and Auchiniarn Road and is covered by a legal agreement as part of their planning permission.

It’s expected to be complete in around six months.

Phases one and two of the relief road, which are within Glasgow, are already complete and connect drivers to the Robroyston roundabout and onto the M80.

There will be five phases in total.

* Have you got a story, picture or comment? E-mail kirkyherald@jnscotland.co.uk

Alternatively you can call the newsdesk 0141 775 0040, find us on Facebook or visit us on Twitter

Or you can log in below and have you say on the site...

 

Comments

 
 

Back to the top of the page